Change Order Disputes: Getting Paid for Extra Work

Published November 7, 20265 min readSources checked November 6, 2026

Draft for attorney review

Short answer

It depends on what the contract says and what the owner did. Texas courts generally enforce clauses requiring a signed written change order before extra work is compensable. But the requirement can be waived: an owner or general contractor who directed the work, watched it being done, accepted its benefit and paid for other unsigned changes may be held to have given up the writing requirement. Where the contract claim fails, a claim for the reasonable value of work knowingly accepted may still succeed. Since September 2023 a contractor can also refuse unsigned owner-directed extra work once it exceeds ten percent of the contract amount.

Tate Modern spiral staircase - 2025-09-27

What does a typical change order clause require?

A written order, signed by the owner or its authorized representative, describing the change, the price adjustment and the time adjustment, before the work is performed. Many contracts add that the contractor waives any claim for extra compensation not submitted within a set number of days, and that no oral instruction, course of dealing or payment constitutes a waiver of the writing requirement. Standard forms also recognize a construction change directive, by which the owner can order work to proceed before price is agreed, with the price set later by the contract's method.

These clauses exist because owners want to control cost and because the field is full of people who say yes. Courts in Texas treat them as ordinary contract terms and enforce them. The questions in a dispute are therefore whether the clause was satisfied, whether it was waived, and whether another theory of recovery applies.

When has the writing requirement been waived?

When the party who insisted on it acted inconsistently with it. Waiver is the intentional relinquishment of a known right, and it can be shown by conduct. Facts Texas courts have found persuasive include an owner's representative directing the change in the field, the owner's knowledge that the work was being done and acceptance of it, a pattern of paying for other changes that were never put in a signed order, and emails or meeting minutes acknowledging the extra scope and price. A clause that says conduct can never waive the requirement makes the argument harder but not impossible, because that clause too can be waived.

What does not help: the contractor's own belief that the work was extra, a conversation with a superintendent who had no authority to commit the owner, or a change the contract already required as part of the base scope. Authority is a frequent battleground; the contract usually names who can approve changes, and a project manager's verbal approval may not bind the owner.

Example

Suppose a Dallas drywall subcontractor is told by the general contractor's superintendent to add a second layer of board on the corridor walls after the owner's acoustical consultant changed the detail. The subcontractor emails the superintendent a price the same day, receives a reply of "proceed, we'll paper it," and finishes the work, which the owner's architect inspects and approves. Three months later the general contractor refuses the invoice because no change order was signed. The subcontractor's claim rests on the written direction to proceed, the general contractor's knowledge and acceptance, and the architect's approval. If the general contractor has paid two earlier changes on the same project without signed orders, the waiver argument is considerably stronger.

What if the contract claim fails?

Texas allows recovery of the reasonable value of services or materials furnished and knowingly accepted when there is no enforceable contract covering them. The limit is that quantum meruit is generally unavailable when an express contract covers the same work, which is exactly what an owner argues when the contract has a change order clause. The claim fits best when the extra work falls outside the contract's scope entirely, or when the contract has been abandoned or terminated. Quantum meruit and unjust enrichment in Texas explains the elements and the express-contract bar.

Can I refuse to do unsigned extra work?

Yes, within limits, and since 2023 by statute. Under Tex. Prop. Code § 28.0091, a contractor or subcontractor may elect not to proceed with additional work directed by the owner if it has not received a written, fully executed change order for that work and the value of that work, together with earlier owner-directed additional work still without an executed change order, exceeds ten percent of the contractor's or subcontractor's original contract amount. A party that properly makes the election is not responsible for damages associated with it. The statute applies to contracts entered into on or after September 1, 2023.

Below the ten percent threshold, the contract governs. Many contracts require the contractor to proceed with directed changes and resolve price later, and stopping work over a change order dispute can be a breach. The practical path is to issue a written notice that the work is considered a change, state the price and time impact, request a change order or directive, and proceed under protest if the contract requires it, preserving the claim. The Texas Prompt Payment Act covers the chapter the ten percent rule sits in.

What documentation wins change order disputes?

  • A written notice, sent the day the extra work is directed, that identifies the work as a change and states the expected cost and schedule effect, sent to the person the contract names.
  • The direction itself: the email, RFI response, revised drawing, consultant memo or field order that caused the change.
  • Daily reports and timesheets that separate change order labor and materials from base scope.
  • Photographs before, during and after, with dates.
  • Meeting minutes and pay applications that list the pending change and were not objected to.
  • The contract's notice and claim deadlines, with proof each was met.

Documenting a construction dispute covers the full record.

Can extra work go into a lien?

Yes, if it was furnished to the improvement under the claimant's contract, including changes reasonably contemplated by it; the lien statute's definition of completion expressly includes extras and change orders (Tex. Prop. Code § 53.001). The amount claimed must be what is owed, so a lien that includes disputed extras should be supported by the same documentation. An inflated lien invites a summary motion to remove and, where intent to defraud is shown, fraudulent lien liability; how mechanic's liens work in Texas explains the limits.

Attorney's fees and the forum

A contractor who recovers on a written or oral contract claim for extra work may recover reasonable attorney's fees from an individual or organization under Tex. Civ. Prac. & Rem. Code § 38.001, after presenting the claim and allowing 30 days. Most construction contracts also carry a prevailing-party fee clause and an arbitration clause, so the dispute may end up before an arbitrator rather than a Dallas County jury. Tina Wysk represents contractors, subcontractors and owners in change order and extra work disputes in Dallas–Fort Worth.

Questions on this topic

Can I get paid for extra work in Texas without a signed change order?

Sometimes. If the contract requires a signed change order, the owner will rely on it, and courts enforce such clauses. You can still recover if the owner waived the requirement by directing the work, knowing it was being done, accepting it and treating other unsigned changes the same way, or if the work falls outside the contract so that a claim for its reasonable value is available. The written record of the direction and acceptance decides it.

Does a text message or email approving extra work count as a change order?

It can satisfy a writing requirement if it comes from someone with authority to approve changes and describes the work and price, though contracts often require a specific form and signature. Even where it falls short of a formal change order, the message is strong evidence of direction and knowledge for a waiver argument. Save it, and follow up with a written change order request the same day.

Can a contractor stop work until a change order is signed?

Under Property Code § 28.0091, for contracts since September 1, 2023, a contractor or subcontractor may decline owner-directed additional work once unsigned owner-directed changes exceed ten percent of its original contract amount, without liability for that election. Below that, the contract controls, and many contracts require the contractor to proceed with directed changes and resolve price afterward. Stopping in breach of such a clause creates its own claim against the contractor.

What is the difference between a change order and a construction change directive?

A change order is a signed agreement among the parties on the scope, price and time of a change. A construction change directive is a written order from the owner, usually through the architect, telling the contractor to proceed with a change before the price is agreed, with the adjustment determined later under the contract's method. A directive avoids a stoppage but leaves the price open, which is where many disputes begin.

How long do I have to submit a claim for extra work?

Check the contract first: many require notice of a claim within a set number of days after the event, and some make late claims waived. Those clauses are generally enforced, though waiver arguments exist. The statutory deadline for a breach of contract suit is generally four years, and lien deadlines run in months from the work, so the contract deadline is almost always the shortest and the one to meet.

Next step

Discuss a construction payment or defect dispute

Tina Wysk handles construction disputes for businesses and individuals in Dallas state and federal courts. A short conversation is usually enough to see where you stand.

Sources

  1. Tex. Prop. Code § 28.0091 (election not to proceed with unsigned owner-directed additional work above ten percent of the original contract amount; no liability for the election (effective September 1, 2023))
  2. Tex. Civ. Prac. & Rem. Code § 38.001 (attorney's fees on an oral or written contract claim against an individual or organization)
  3. Tex. Prop. Code § 53.001 (definition of completion includes extras and change orders reasonably required or contemplated under the contract)
  4. H.B. 3485, 88th Leg. (2023), enrolled (the 2023 act adding § 28.0091, applicable to contracts entered on or after September 1, 2023)

Legal sources last checked November 6, 2026. Statutes and rules change; the date matters.

Tina Wysk

About the author

Tina Wysk

Shareholder, Hallett & Perrin, P.C.. Tina represents businesses and individuals, as plaintiffs and defendants, in contract, partnership, fiduciary duty, fraud, construction, trade secret and investment disputes in Texas state and federal courts and in arbitration.

About Tina

This guide is general information about Texas and federal law for business owners, not legal advice about your situation. Statutes, rules and court decisions change, and small facts change outcomes. Reading it or contacting Tina Wysk through this site does not create an attorney-client relationship.

CallDiscuss Your Matter