Statute of Repose and Limitations for Construction Claims in Texas

Published November 7, 20265 min readSources checked November 6, 2026

Draft for attorney review

Short answer

Texas has two clocks on a construction claim. The statute of limitations runs from when the claim accrued, generally four years for contract and two for negligence, and can be delayed by the discovery rule. The statute of repose runs from substantial completion and cannot: a suit against a contractor or a design professional must be filed within ten years after substantial completion, or six years for a residence built since mid-2023 under a written warranty that meets the statutory minimums. Presenting a written claim within the period extends it by two years (one year under the shorter periods). Fraudulent concealment and willful misconduct are excepted.

View of the curvy staircase in the Tate Modern - geograph.org.uk - 5512368

Limitations or repose: which one applies?

Both, and the earlier bar wins. A statute of limitations starts when a cause of action accrues, which for a construction defect is usually when the defective work was done or delivered, and Texas sometimes delays accrual under the discovery rule for injuries that were inherently undiscoverable. A statute of repose starts on a fixed event, substantial completion, and runs regardless of when the owner knew or could have known about the problem. Repose is designed to give builders and designers a point after which the project is closed, and courts apply it as written.

So an owner who discovers a defect in year nine may still be inside repose but outside limitations if the defect should have been found earlier; an owner who discovers a hidden defect in year eleven may have a live limitations argument and still be barred by repose.

The limitations periods

  • Breach of contract and breach of warranty: generally four years, under the residual period in Tex. Civ. Prac. & Rem. Code § 16.051, measured from the breach.
  • Negligence causing property damage: generally two years under § 16.003.
  • Residential Construction Liability Act claims follow the limitations period of the underlying claim, with the statutory notice period tolling in some circumstances.

The contract may shorten these periods or set its own accrual date, and warranty periods in the contract are separate from both.

The repose periods under § 16.009 and § 16.008

DefendantClaimPeriod after substantial completionStatute
Contractor, subcontractor or anyone who constructed or repaired the improvementDefective or unsafe condition of the property or improvement, or a deficiency in the construction or repair10 years§ 16.009(a)
Same, when the claimant is a governmental entitySame8 years (with exceptions for certain transportation and civil works contracts)§ 16.009(a-1)
Contractor on a new residence, or an alteration, repair or addition to a residence, who gave a qualifying written warrantySame6 years§ 16.009(a-2), (a-3)
Registered or licensed architect, engineer, interior designer or other covered design professional who designed, planned or inspected the improvementDefective or unsafe condition of the property, improvement or equipment10 years (8 for governmental claimants)§ 16.008

The periods cover suits for property damage, personal injury, wrongful death, contribution and indemnity (§§ 16.008(b), 16.009(b)). They do not shorten a longer written warranty or contract term, and they do not protect a person in actual possession or control of the property when the harm occurs (§ 16.009(e)).

The six-year residential period since 2023

House Bill 2024, effective June 9, 2023, added the shorter period. It applies when the defendant is a contractor, as the Residential Construction Liability Act defines that term, and the claim arises from a new residence, an alteration, repair or addition to an existing residence, or an appurtenance, where the contractor provided a written warranty with at least these terms (§ 16.009(a-3)):

  • one year for workmanship and materials;
  • two years for plumbing, electrical, heating and air-conditioning delivery systems; and
  • six years for major structural components.

A residence for this purpose is a detached one- or two-family dwelling, a townhouse, or an accessory structure, generally up to three stories (§ 16.009(a-4)). A contractor who gave no warranty, or a warranty that falls short of the minimums, keeps the ten-year period.

When does the clock start?

At substantial completion of the improvement, or for equipment, the beginning of its operation. Substantial completion is not defined in the repose statute; contracts usually define it as the date the owner can use the work for its intended purpose, often marked by a certificate of substantial completion or a certificate of occupancy. Where the contract is silent, the date becomes a fact question, and the parties argue over punch lists, partial occupancy and later repairs. Warranty and repair work after substantial completion does not restart the clock on the original work, though a separate repair may have its own repose period.

Example

Suppose a Denton apartment complex received its certificate of substantial completion on August 1, 2016. In early 2026 the owner's engineer finds that the balconies were framed without the specified flashing. The ten-year repose period ends August 1, 2026. A suit against the general contractor filed in July 2026 is inside repose, and the owner then has to win the limitations argument, probably by showing the defect was inherently undiscoverable. If the owner instead sends a written claim to the contractor in July 2026, repose is extended two years to July 2028, giving time to investigate. A suit first filed in September 2026, with no claim letter, is barred regardless of discovery.

How can the period be extended?

Only in the ways the statute allows:

  • Written claim. Presenting a written claim for damages, contribution or indemnity to the contractor or design professional during the repose period extends it for two years from the date the claim is presented, or one year under the eight-year and six-year periods (§§ 16.008(c), 16.009(c)). A short, dated letter describing the defect and demanding compensation does the job; it is the single most useful step when a ten-year date is near.
  • Injury in the last year. If the damage, injury or death occurs during the tenth year (or the last year of a shorter period), suit may be filed within two years after the cause of action accrues (§ 16.009(d)).
  • Exceptions. Repose does not bar a claim based on willful misconduct or fraudulent concealment in connection with the work, or an action on a written warranty, guaranty or contract that expressly provides a longer effective period (§ 16.009(e)).

Agreements between the parties cannot extend repose in the way they can extend limitations with a tolling agreement, because repose is a substantive cutoff rather than a procedural one; whether a particular agreement is treated as a contract claim with its own longer period is a question for counsel.

How repose plays out in a defect case

For owners, the lesson is to calendar substantial completion on every project and to send a written claim before year ten even if the investigation is incomplete. For contractors and designers, repose is an affirmative defense: it must be pleaded, and it is often raised by summary judgment with the certificate of substantial completion attached. Multi-party cases can split: the general contractor may be inside the ten-year period because of an extension letter while a subcontractor who never received one is out. Construction defect claims in Texas covers who is liable and what the claims look like, and how long you have to sue for breach of contract covers the four-year period in detail.

Claims against architects and engineers also require a certificate of merit at filing, which takes time to obtain; an owner near the repose date should start that process early. The certificate of merit rule explains it. Tina Wysk handles construction defect and design claims for owners, contractors and design firms in construction litigation in Dallas.

Questions on this topic

What is the statute of repose for construction in Texas?

Ten years after substantial completion for claims against contractors and others who constructed or repaired an improvement, and ten years for claims against registered architects, engineers and other covered design professionals. Governmental claimants have eight years. Since June 2023, six years applies to claims against a contractor on a residence who provided a written warranty meeting the statutory minimums.

Does the discovery rule stop the statute of repose?

No. The discovery rule can delay when a limitations period begins by postponing accrual until the injury was discoverable, but repose runs from substantial completion regardless of knowledge. That is the point of repose. The only ways around it are the statutory extension for a written claim presented within the period, the last-year rule, and the exceptions for willful misconduct, fraudulent concealment, and longer written warranties or contracts.

Does sending a demand letter extend the statute of repose?

Yes, if it is presented within the repose period and is a written claim for damages, contribution or indemnity against the contractor or design professional. The period is then extended two years from presentation under the ten-year rule, or one year under the eight-year and six-year rules. The letter should describe the defect, identify the project and demand compensation, and be sent in a way that proves the date.

Which warranty terms qualify a builder for the six-year repose period?

A written warranty of at least one year for workmanship and materials, two years for plumbing, electrical, heating and air-conditioning delivery systems, and six years for major structural components, given by a contractor on a new residence or an alteration, repair or addition to one. A warranty with shorter terms, or no written warranty, leaves the contractor under the ten-year period.

What counts as substantial completion for the Texas statute of repose?

The statute does not define it, so courts look to the contract and the facts: typically the date the owner could occupy or use the improvement for its intended purpose, often shown by a certificate of substantial completion or a certificate of occupancy. Punch list work and later warranty repairs do not restart the period for the original work. When the date is disputed, it becomes a fact question in the case.

Next step

Discuss a construction payment or defect dispute

Tina Wysk handles construction disputes for businesses and individuals in Dallas state and federal courts. A short conversation is usually enough to see where you stand.

Sources

  1. Tex. Civ. Prac. & Rem. Code § 16.009 (ten-year repose for construction and repair; eight years for governmental claimants; six years for qualifying residential warranties; extension, last-year rule and exceptions)
  2. Tex. Civ. Prac. & Rem. Code § 16.008 (ten-year repose for registered architects, engineers and other design professionals, with written-claim extension)
  3. H.B. 2024, 88th Leg. (2023), enrolled (the 2023 amendment adding the six-year residential period, effective June 9, 2023)
  4. Tex. Civ. Prac. & Rem. Code §§ 16.003, 16.051 (two-year and residual four-year limitations periods)
  5. Tex. Civ. Prac. & Rem. Code § 150.002 (certificate of merit required for claims against licensed design professionals)

Legal sources last checked November 6, 2026. Statutes and rules change; the date matters.

Tina Wysk

About the author

Tina Wysk

Shareholder, Hallett & Perrin, P.C.. Tina represents businesses and individuals, as plaintiffs and defendants, in contract, partnership, fiduciary duty, fraud, construction, trade secret and investment disputes in Texas state and federal courts and in arbitration.

About Tina

This guide is general information about Texas and federal law for business owners, not legal advice about your situation. Statutes, rules and court decisions change, and small facts change outcomes. Reading it or contacting Tina Wysk through this site does not create an attorney-client relationship.