Construction & Payment Disputes
Texas Mechanic's Lien Deadlines: Notices and Filing Dates
Draft for attorney review
Short answer
For projects whose original contract was signed on or after January 1, 2022, a Texas lien claimant has these deadlines. A subcontractor or supplier sends the notice of claim to the owner and original contractor by the 15th day of the third month after each month of unpaid work (second month on a residential project). Every claimant files the lien affidavit by the 15th day of the fourth month after the month the work was last performed, or the third month for residential work. Suit to foreclose must be filed within one year after the last day the affidavit could have been filed.

Which set of rules applies to my project?
The date of the original contract between the owner and the general contractor decides it, not the date of your own subcontract. House Bill 2237 rewrote the notice and deadline sections of Property Code chapter 53 effective January 1, 2022, and the new rules apply to projects whose original contract was entered into on or after that date. A project under an original contract signed in 2021 is still governed by the earlier version, which had a separate second-month notice on commercial jobs and different retainage notices. This article states the current rules as of 2026; if the prime contract predates 2022, have counsel check the old text.
Two terms matter throughout. A residential construction project is work on a house, duplex, triplex, fourplex or condominium unit that an owner uses or intends to use as a dwelling (§ 53.001); apartments built for an investor are non-residential for these deadlines. An original contractor contracted directly with the owner; everyone else is a derivative claimant and has an extra notice step.
The deadlines in one table
| Step | Who | Non-residential | Residential | Statute |
|---|---|---|---|---|
| Notice of claim for unpaid labor or materials, to owner and original contractor | Derivative claimants | 15th day of the third month after each month the work was performed or materials delivered | 15th day of the second month | § 53.056 |
| Notice of claim for unpaid retainage, to owner and original contractor | Derivative claimants with contractual retainage | The earlier of the 30th day after the claimant's own contract is completed, terminated or abandoned, or the 30th day after the original contract is terminated or abandoned | § 53.057 | |
| Lien affidavit recorded with the county clerk | Original contractor | 15th day of the fourth month after the month the original contract was completed, terminated or abandoned | 15th day of the third month | § 53.052(a) |
| Lien affidavit recorded with the county clerk | Derivative claimants | 15th day of the fourth month after the later of the last month of labor or materials, or the month undelivered specially fabricated materials would normally have been delivered | 15th day of the third month | § 53.052(b), (c) |
| Lien affidavit for retainage only | Derivative claimants | 15th day of the third month after the month the original contract was completed, terminated or abandoned | § 53.052(d) | |
| Copy of the filed affidavit to the owner (and to the original contractor if the claimant is not one) | All claimants | Fifth day after the affidavit is filed | § 53.055 | |
| Suit to foreclose the lien, in the county where the property sits | All claimants | First anniversary of the last day the affidavit could have been filed; extendable to the second anniversary of the filing by a recorded written agreement with the current owner made before the first period runs | § 53.158 | |
The affidavit deadline is a last day, not a target. Nothing stops a claimant from filing as soon as a payment is late, and early filing avoids the argument over which month the work ended.
How do I count the months?
Start with the calendar month in which the unpaid work was performed. Count forward the stated number of months. The deadline is the 15th of that month. Suppose a subcontractor's last unpaid work on a commercial project was in March. The notice of claim for March is due by June 15 (the third month after March). The lien affidavit is due by July 15 (the fourth month after March). Work performed in April has its own notice deadline of July 15, so a claimant unpaid for several months sends a notice for each month or a combined notice before the earliest date runs.
If the last day falls on a Saturday, Sunday or legal holiday, the period extends to the next day that is not one of those (§ 53.003(e)). Do not rely on that extension if you can avoid it; a county clerk's office closed for an unexpected reason is a bad place to learn how a court will treat a filing the following day.
How must the notices be delivered?
In person, by certified mail, or by any other traceable private delivery or mailing service that can confirm proof of receipt (§ 53.003(b)). A notice sent by certified mail is considered given when deposited in the mail, properly addressed and stamped (§ 53.003(c)), so the mailing date, not the receipt date, is what must fall on or before the 15th. Keep the receipt. A notice the recipient actually receives is effective however it was sent (§ 53.003(d)), but proving actual receipt of an email is harder than producing a certified mail receipt.
Since 2022 the notice of claim must be in substantially the form the statute prints, with the project, claimant, type of work, original contractor, the party the claimant contracted with, the amount and the claimant's contact details (§ 53.056(a-2)). An invoice may be attached but does not replace the form.
Does the retainage notice replace the monthly notice?
No. They cover different money. The monthly notice of claim covers unpaid progress payments. The retainage notice covers the contractual retainage the claimant's own contract lets the hiring party hold back, to the extent that amount was not already included in a monthly notice (§ 53.057(a)). A subcontractor who sends timely monthly notices but never sends the retainage notice can lose the lien on the retainage, which is often the largest unpaid piece at the end of a job. The retainage notice is due within 30 days of the claimant's own contract ending, which can be months before the project ends.
Example
Suppose an electrical subcontractor on a non-residential project in Dallas finishes its scope on September 20 and is owed its August and September progress billings plus ten percent retainage. The notice of claim for August is due November 15; for September, December 15. The retainage notice is due October 20, the 30th day after its contract was completed. The lien affidavit for the progress billings is due January 15, the fourth month after September; the affidavit for retainage is due the 15th day of the third month after the month the original contract is completed, which may be later. Suit to foreclose must be filed within a year after each affidavit's last filing day.
What if a deadline was missed?
The lien is lost for that money, but the debt is not. A claimant who missed the notice or affidavit deadline still has a breach of contract claim against the party that hired it, and possibly a claim under the Prompt Payment Act or the Construction Trust Fund Act. The owner's property is simply no longer security. Owners who receive a late lien affidavit have a summary procedure to remove it, which removing an invalid lien from Texas property describes.
Some deadlines cannot be rescued by filing again. An affidavit filed after the statutory date is late no matter how many times it is re-recorded. The suit deadline in § 53.158 is a limitations period, and a suit filed only to clear a lien after it expires does not revive the claimant's right to foreclose (§ 53.158(a-1)).
Related dates that are not lien deadlines
- Owner's reserved funds: ten percent of the contract price, held during the work and for 30 days after completion (§ 53.101). A claimant who wants a share of that fund must perfect its lien within that window or send the notices on time.
- Public projects: no lien on government property; payment bond notices under Government Code chapter 2253 have their own calendar. Payment bond claims on Texas public projects covers it.
- Prompt Payment Act: owner pays within 35 days of a pay request, contractor pays subcontractors within seven days of receiving payment, on private projects (Tex. Prop. Code § 28.002). These are payment deadlines that trigger interest, not lien deadlines.
For what the lien does once perfected, and the owner's side of the ledger, see how mechanic's liens work in Texas. Tina Wysk advises contractors and owners on lien perfection and lien defense in Dallas–Fort Worth.
Questions on this topic
Is the Texas lien deadline measured from the invoice date or the work date?
From the month the labor or materials were furnished, not the invoice date or the due date. The affidavit deadline for a derivative claimant runs from the month in which the claimant last furnished labor or materials, and each notice of claim runs from the month the unpaid work was performed. A late invoice does not move the deadline, so billing promptly protects the lien.
Do original contractors have to send a pre-lien notice in Texas?
No. A contractor who contracted directly with the owner perfects its lien by filing the affidavit on time and sending the owner a copy within five days. The monthly notice of claim and the retainage notice are requirements for derivative claimants, meaning subcontractors, sub-subcontractors and suppliers, because the owner may not know they exist.
Did the 2022 changes make the Texas lien deadlines shorter?
They simplified them more than they shortened them. For contracts signed on or after January 1, 2022, the separate second-month notice on commercial projects was eliminated, one notice now goes to both the owner and the original contractor by the 15th of the third month, the notices must follow statutory forms, and the time to sue became one year with a possible extension to two by agreement. Residential projects kept their shorter second-month notice and third-month affidavit.
Can the owner and I agree to extend a lien deadline?
Only one of them. The period to file suit to foreclose can be extended to the second anniversary of the affidavit filing by a written agreement with the then-current record owner, signed before the one-year period ends and recorded with the county clerk. The notice and affidavit deadlines cannot be extended by agreement; a claimant who wants to keep working with a slow-paying owner has to file on time and negotiate afterward.
Can I send one notice covering several months of unpaid work?
Yes, as long as the notice reaches the owner and original contractor by the earliest month's deadline and identifies the amounts claimed. A single notice sent by the 15th of the third month after the oldest unpaid month covers that month and the later ones. Waiting to combine months is what causes the oldest month to fall off, so most claimants send a notice as soon as any month goes unpaid.
Sources
- Tex. Prop. Code §§ 53.001, 53.052 (definitions of residence and residential construction project; affidavit deadlines: 15th day of the fourth month (non-residential), third month (residential), retainage affidavit)
- Tex. Prop. Code § 53.056 (derivative claimant notice to owner and original contractor by the 15th of the third month (second month residential), statutory form)
- Tex. Prop. Code § 53.057 (retainage notice due within 30 days of the claimant's contract or the original contract ending)
- Tex. Prop. Code § 53.003 (delivery methods, certified mail effective on deposit, weekend and holiday extension)
- Tex. Prop. Code § 53.158 (suit to foreclose within one year of the last filing day, extension to two years by recorded agreement)
- H.B. 2237, 87th Leg. (2021), enrolled (the 2021 amendments to chapter 53, effective January 1, 2022, applicable to original contracts entered on or after that date)
Legal sources last checked November 6, 2026. Statutes and rules change; the date matters.
This guide is general information about Texas and federal law for business owners, not legal advice about your situation. Statutes, rules and court decisions change, and small facts change outcomes. Reading it or contacting Tina Wysk through this site does not create an attorney-client relationship.