Short answer

A specialty contractor who is not paid has the same tools as any Texas subcontractor, but often sits lower in the chain, with extra notices and more defenses to overcome. On a private project the lien notice goes to the owner and the original contractor by the 15th day of the third month after each unpaid month, the retainage notice within 30 days of finishing, and the Prompt Payment Act entitles the trade to payment within seven days of the general contractor being paid. On public work the payment bond replaces the lien. The disputes concern back-charges, verbal extras, pay-if-paid clauses and licensing, and each has an answer.

View of the curvy staircase in the Tate Modern - geograph.org.uk - 5512368

Why trades are in a different position

An electrical, mechanical or plumbing contractor almost never contracts with the owner. It works for a general contractor, sometimes for another subcontractor, and the owner who holds the money may not know it exists. Its scope interfaces with every other trade, so when something is late or wrong it is blamed for coordination failures it did not cause. It carries high material costs that are billed before they are paid for. And it is licensed, which gives the other side one more thing to check. Each of those facts shapes the payment fight.

The notice calendar for a trade subcontractor

On a private project the lien is the pressure point, and it depends on notices the trade must send even while the relationship is still cordial. The current rules apply to projects whose original contract was signed on or after January 1, 2022.

ProjectNoticeDeadline
Private, non-residentialNotice of claim to the owner and the original contractor, in the statutory form (Prop. Code § 53.056)15th day of the third month after each month of unpaid work (second month on residential)
PrivateNotice of claim for unpaid retainage to the owner and original contractor (§ 53.057)30th day after the trade's own contract is completed, terminated or abandoned
PrivateLien affidavit recorded with the county clerk (§ 53.052), copy to owner and original contractor within five days15th day of the fourth month after the last month of work (third month residential)
Texas publicSworn notice of claim to the prime contractor and the surety (Gov't Code § 2253.041); a trade working under another subcontractor also notifies the prime by the second month (§ 2253.047)15th day of the third month after each unpaid month; second-tier notice by the 15th day of the second month
FederalMiller Act notice to the prime contractor, for trades with no contract with the primeWithin 90 days after the trade's last labor or material

Texas mechanic's lien deadlines covers the counting rules and the one-year suit deadline. The point for a trade is simpler: a notice for every unpaid month, sent by a method that proves mailing, starting with the first month that is late, costs almost nothing and preserves everything.

When must the general contractor pay me?

Within seven days of being paid. Under the Prompt Payment Act a contractor that receives payment from the owner must pay each subcontractor its share not later than the seventh day after receipt, and each subcontractor must pass payment down on the same schedule (Prop. Code § 28.002). Late amounts earn interest at 1.5 percent a month and a court may award attorney's fees. The general contractor may withhold only for a good faith dispute, and no more than 100 percent of the disputed difference on commercial property or 110 percent on a single-family residence, duplex, triplex or fourplex (§ 28.003); the undisputed balance is still due in seven days. On a private non-residential project an unpaid trade may also suspend work ten days after giving written notice of nonpayment and intent to suspend (§ 28.009). The Texas Prompt Payment Act sets out each of these.

The practical problem is knowing when the owner paid. Ask the owner's representative or the lender's inspector which draws have funded; on many projects the owner's pay application record is available for the asking, and it starts the seven-day clock. The general contractor was paid but did not pay me covers the trust fund claim against the contractor's principals when the money went elsewhere.

Back-charges and set-offs

A back-charge is the general contractor's claim that it incurred cost because of the trade's work, deducted from the trade's payment. Three questions decide whether it sticks. Does the subcontract allow it, and on what conditions, such as prior written notice and a chance to correct the work? Was the notice given before the cost was incurred? And can the general contractor prove the cost with invoices, time records and photographs, rather than a round number? A back-charge first disclosed when the final payment is withheld, with no earlier notice and no backup, is a weak set-off, and the trade should demand the documentation in writing and dispute the amount in writing within whatever period the subcontract allows.

A back-charge is also a good faith dispute under the Prompt Payment Act only to the extent of the amount reasonably in dispute. Withholding the entire draw over a back-charge worth a fraction of it is over-withholding, and interest runs on the excess.

Example

Suppose an HVAC subcontractor on a Richardson medical office building is owed its final two draws plus retainage. The general contractor's closeout letter deducts a back-charge for a controls subcontractor it hired to finish commissioning, with no earlier notice and a single-line amount. The HVAC contractor responds in writing within the subcontract's dispute period, requests the controls invoices and daily tickets, sends its lien notices for both unpaid months by certified mail to the owner and the general contractor, sends the retainage notice within 30 days of finishing, and records the lien affidavit on time. The general contractor now has to prove the cost it incurred and explain why it gave no notice, while the owner is holding reserved funds against a perfected lien. Most such disputes resolve once both facts are on the table.

Verbal extras and scope creep

Trades do more extra work than any other participant: added circuits, relocated equipment, resequencing to accommodate other trades, repairs to work others damaged. The subcontract almost always requires a written change order before extra work is paid, and the general contractor almost always directs the work verbally and promises paperwork later. The answers are procedural. Get a time-and-material ticket signed on site the same day. Confirm every verbal direction by email that evening, stating that the work is extra and will be billed. Send the written change request the subcontract requires, within its deadline. Keep separate cost codes for each extra. Since 2023, Property Code § 28.0091 also lets a subcontractor decline to proceed with owner-directed extra work that lacks a signed change order once the unsigned extras exceed ten percent of its contract amount, without liability for the refusal. Change order disputes covers how unsigned extras are recovered when the paperwork never came.

Pay-if-paid and pay-when-paid clauses

Many subcontracts say the trade is paid only when, or only if, the general contractor is paid by the owner. Texas limits these clauses. Under Business and Commerce Code chapter 56 a contingent payment clause cannot be enforced to the extent the owner's nonpayment results from the general contractor's own failure to meet its contractual obligations, and in other situations the statute lists. Pay-when-paid and pay-if-paid clauses in Texas explains when the clause shifts the owner's credit risk to the trade and when it does not. The lien and the bond claim exist regardless of the clause; the owner's property secures the trade's work whether or not the general contractor has been paid.

Licensing

Electrical work in Texas may be performed or offered only by a person or business holding the appropriate license under Occupations Code chapter 1305 (§ 1305.151). Plumbing is licensed under chapter 1301 and air conditioning and refrigeration contracting under chapter 1302. In a payment dispute, expect the other side to check that the license was current, in the correct name, and that permits were pulled under it. A lapse or a mismatch between the licensed entity and the contracting entity becomes a defense to payment and a complaint to the licensing agency, so the license, the contracting entity and the permits should match before the first invoice goes out.

Public and bonded projects

On a Texas public project the trade cannot lien the property and claims against the prime contractor's payment bond instead, with the notices in the table above and suit within one year after the notice is mailed. A trade working under another subcontractor is a second-tier claimant and has the extra second-month notice to the prime. On federal projects the Miller Act bond and its 90-day notice apply. Private projects sometimes carry a payment bond too, which gives the trade a bond claim alongside the lien.

Common mistakes by trade contractors

  • Waiting for the final pay application before sending any lien notice, when each unpaid month has its own deadline.
  • Sending the retainage notice when the project ends rather than within 30 days of the trade's own completion.
  • Signing an unconditional lien waiver for a draw that has not cleared.
  • Accepting back-charges in silence, or disputing them by phone.
  • Performing extras on a handshake without a signed ticket or a same-day email.
  • Contracting under a trade name while the license sits with a different entity.

Tina Wysk represents electrical, mechanical, plumbing and other specialty contractors, and the general contractors and owners on the other side, in payment disputes in Dallas–Fort Worth.

Questions on this topic

Can an electrical subcontractor file a lien in Texas even though the general contractor was paid in full?

Yes, if its notices were sent on time. The owner's payment to the general contractor does not extinguish a subcontractor's lien rights; it changes what the lien attaches to. A subcontractor whose notice of claim reached the owner by the 15th day of the third month after the unpaid work has a lien on funds the owner should have withheld after that notice, and every subcontractor has a lien on the 10 percent the owner must reserve for 30 days after completion. An owner who paid everything out early can be liable to the extent of what should have been held.

How long does a general contractor have to pay a subcontractor in Texas after the owner pays?

Seven days. Under Property Code § 28.002 a contractor that receives payment from the owner must pay each subcontractor the portion of that payment attributable to the subcontractor's work not later than the seventh day after receiving it, and each lower tier passes payment down on the same schedule. Late payment accrues interest at 1.5 percent a month, and only a good faith dispute, within the statutory cap, justifies withholding.

Can the general contractor back-charge me for work it says I did wrong?

Only on the terms the subcontract sets, and only for costs it can prove. Most subcontracts allow a back-charge after written notice and a chance to correct the work, and a back-charge announced for the first time at final payment, without earlier notice or documentation, is open to challenge. Dispute it in writing within the subcontract's period, request the invoices and time records behind it, and remember that only the reasonably disputed amount may be withheld under the Prompt Payment Act.

Will I get paid for extra electrical work the superintendent told me to do verbally?

It depends on the subcontract's change clause and on your paperwork. If the subcontract requires a signed change order, a verbal direction is not one, and the general contractor will say so. Trades recover verbal extras by getting time-and-material tickets signed on site, confirming the direction by email the same day, sending the written change request the subcontract requires, and proving the cost from separate job cost codes. Without those, the claim depends on whether the other side's conduct waived the written requirement, which is harder.

Does a lapsed or mismatched license affect my right to be paid in Texas?

It gives the other side an argument and a complaint to make, so treat it seriously. Electrical, plumbing and air conditioning work must be performed by appropriately licensed persons or businesses under Occupations Code chapters 1305, 1301 and 1302. In a payment dispute the general contractor or owner will check whether the license was current, held by the contracting entity and used for the permits. A clean match removes the issue; a mismatch invites a defense whose outcome depends on the facts and should be reviewed by counsel before suit.

Next step

Discuss a construction payment or defect dispute

Tina Wysk handles construction disputes for businesses and individuals in Dallas state and federal courts. A short conversation is usually enough to see where you stand.

Sources

  1. Tex. Prop. Code §§ 53.052, 53.056, 53.057 (subcontractor notice of claim by the 15th day of the third month, retainage notice within 30 days of the claimant's contract ending, lien affidavit by the fourth month)
  2. Tex. Prop. Code §§ 28.002–28.004, 28.009, 28.0091 (seven-day pass-through payment, good faith withholding caps, 1.5 percent monthly interest, suspension after ten days' notice, right to decline unsigned extras above ten percent)
  3. Tex. Gov't Code §§ 2253.041, 2253.047 (public project bond notice to prime and surety by the 15th day of the third month; second-tier notice to the prime by the 15th day of the second month)
  4. Tex. Bus. & Com. Code ch. 56 (limits on enforcing contingent payment clauses, including where nonpayment results from the contractor's own failure to perform)
  5. Tex. Occ. Code § 1305.151 (electrical work may be performed or offered only under an appropriate license)
  6. Tex. Occ. Code chs. 1301, 1302 (licensing of plumbers and of air conditioning and refrigeration contractors)

Legal sources last checked November 6, 2026. Statutes and rules change; the date matters.

Tina Wysk

About the author

Tina Wysk

Shareholder, Hallett & Perrin, P.C.. Tina represents businesses and individuals, as plaintiffs and defendants, in contract, partnership, fiduciary duty, fraud, construction, trade secret and investment disputes in Texas state and federal courts and in arbitration.

About Tina

This guide is general information about Texas and federal law for business owners, not legal advice about your situation. Statutes, rules and court decisions change, and small facts change outcomes. Reading it or contacting Tina Wysk through this site does not create an attorney-client relationship.

CallDiscuss Your Matter